Gift Shop and Welcome Center

The front room of the warehouse building is being restored into the new gift shop and welcome center where visitors to the roundhouse will check in for tours. Among the repairs on tap are to remove the drop ceiling and install a new floor along with the addition of heat and air conditioning. Exterior work includes tuck pointing, glass block windows and roof repair.

Live Project Updates

The front room has been cleared of stored parts and materials and tuck pointing of the exterior bricks is underway. Old broken windows have been replaced with glass blocks and the false dropped ceiling is being removed. The floor needs to be replaced completely along with roof repair and interior tuck pointing.

July 25, 2022 - 5:37 pm